Construction Update Articles

Laguna Beach Resort Jomtien

May 2013

Structural work on Building A of Laguna Beach Resort Jomtien is complete. Interior walls are in place up to the 3rd floor, along with primary electric & piping systems.
 
Structural work continues on Building B, with the basement & ground floor complete and work now commencing on the 2nd floor exterior skeleton. 
 
Piling work continues on Building C, with 70% of piles complete.

Structural work on Building A of Laguna Beach Resort Jomtien is complete. Interior walls are in place up to the 3rd floor, along with primary electric & piping systems.   Structural work continues on Building B, with the basement & ground floor complete and work now commencing on the 2nd floor exterior skeleton.    Piling work continues on Building C, with 70% of piles complete.


Click here to view latest updates for Laguna Beach Resort Jomtien in our construction update image library.


November 2012

All piling and foundation works are complete for Building A of Laguna Beach Resort Jomtien. Pouring of concrete for the basement floor is complete and all steel retaining walls are in place for the basement floor. Pouring of concrete for the basement walls of Building A is expected to commence imminently.

Excavation work continues at Building B and work on the foundations has begun. The cutting of piles is in progress, with dynamic load tests complete.

Click here to view latest updates for Laguna Beach Resort Jomtien in our construction update image library.



October 2012

The structural foundations of Building A of Laguna Beach Resort Jomtien are now complete. In early November we will be commencing work on pouring concrete for the basement of Building A. 

Piling is now complete for Building B, with dynamic load tests on the pile structures being undertaken by STS Co., Ltd. Soil has been excavated in order for work on the foundations to commence in mid-November.

All measurements have been taken in order for Building C piling to commence next month.

Click here to view latest updates for Laguna Beach Resort Jomtien in our construction update image library.

Click here to view the June 2012 Laguna Beach Resort Jomtien construction update video.




September 2012

With the on-site sales office now complete, progress continues on the foundations of Laguna Beach Resort Jomtien Building A.
 
The final few piles are being installed for Building B whilst we expect to start piling for Building C on 1st October 2012. The on-site showroom is set to be demolished next month when Building C breaks ground.

laguna beach resort jomtien



July 2012

Laguna Beach Resort Jomtien remains well ahead of schedule since construction began two months early in April 2012. All piling work for building A is complete. Piling for building B is now over 80% complete, expected to complete by the 12th of this month. Work on preparing the foundations for building A has now commenced, with the majority of piles cut and soil excavation works 35% complete. Primary contractor KK Construction has also made rapid progress on the site office, now 90% complete.

laguna beach resort jomtien




June 2012

With the development over 90% sold out since launching in July 2011, construction at Laguna Beach Resort Jomtien commenced in April 2012 following the annual Thai Songkran festival – a full two months ahead of schedule.
 
Since then we have seen rapid progress, with piling work for building A at 80%, expected to complete on June 20th. Piling for building B is now well underway, with expected completion mid-July.
 
Structural work on the foundations and exterior skeleton will commence upon completion of the piling phase, with KK Construction and Engineering Co., Ltd. employed as the primary contractor. 


laguna beach resort jomtien





May 2012
laguna beach resort jomtien

laguna beach resort jomtien